INSTALLATION PROCESS  


Setting the proper expectations is what we are ALL about.

Not all Electric Providers are Created equal and some are more friendlier to Solar than others.  To learn how solar works in your area and to figure out if solar makes sense for you, contact us today about setting you up with one of our solar experts .

PREQUALIFY YOUR HOME NOW!

Let's look behind the scenes of an install.  (Roof Type: Hard Clay Tile)

INSTALLATION IS TYPICALLY

8 TO 12 WEEKS FROM  SIGN UP

STEP INSTALLATION PROCESS
Due to the extensive work that needs to be done by the engineers, installation professionals, the city, and the electric company, GOING SOLAR is not a simple task, but that is exactly what we make seem like. There are multiple trades, permits, PV Solar engineers, electricians, plus many more that are involved in bringing your solar dream come true.


Every customer gets access to their own INSTALL PORTAL, giving them 24/7 access to their project's status.


Here is an approximate guideline to give you the correct expectations for anyone going solar with us.  Keep in mind, we always aim to under-promise and over-deliver because your satisfaction is our primary concern.




PREQUALIFY YOUR HOME NOW!



STEP 1. INITIAL CONSULTATION

(ALL DOCS MUST BE COMPLETE TO MOVE TO NEXT STEP)

 

STEP 2. SITE SURVEY

(IF NEEDED, APPROX. 5-7 DAYS FROM ALL DOCS COMPLETED)

 

STEP 3. DESIGN

(ENGINEERING, CAD DRAWINGS AND INTERCONNECTION FILED WITH ELECTRIC PROVIDER, APPROX. 3-5 WEEKS FROM SITE SURVEY)

 

STEP 4. PERMITTING

(TIMEFRAME CONTROLLED 100% BY LOCAL MUNICIPALITIES, AVG IS APPROX. 3-5 WEEKS FROM DESIGN COMPLETION)

 

STEP 5. INSTALLATION

(APPROX. 2 WEEKS FROM PERMITTING)

 

STEP 6. CITY INSPECTS

(TIMEFRAME CONTROLLED 100% BY LOCAL MUNICIPALITIES, 3-5 WEEKS FROM INSTALLATION)

 

STEP 7. UTILITY CONNECTS

(TIMEFRAME CONTROLLED 100% BY LOCAL MUNICIPALITIES, AVG IS APPROX. 3-5 WEEKS FROM CITY INSPECTION)

 

   YOU ARE NOW SAVING MONEY!